← moviant.ai · Get your free First Read

Moviant AI · Compass First Read

First Read: cash not needed · parts running short

Example Chassis & Stampings Pvt Ltd (fictional) · Plant P100, Pune
Data date (4 reports): 9 Oct 2026 · files in 10 Oct = day 1
Your last MRP run: 8 Oct 2026
Page date: 15 Oct 2026 · working day 5
Confidential · for the named signer

Scope: MRP controllers 101–106, 82% of your ₹14.6 Cr stock value. Valued at your own book value; no purchase prices used. 8 weeks = 45 working days on your plant calendar (6-day week, 3 Diwali holidays); longer for long-lead parts.

₹74.1L of cash your own SAP plan does not need in the next 8 weeks, and you can act on it now: ₹46.8L of orders not yet delivered, which buyers can ask suppliers to push back or cancel, and ₹27.3L of stock to move.

Your MRP flags many of these; this page puts them in ₹, ranks them and names an owner. They follow schedule changes, order sizes and lead times, not planning errors. Total not needed in 8 weeks: ₹102.2L.

Push back · orders

₹46.8L

28 order lines, not yet delivered. Ask suppliers to move them to the date you need them, or cancel.

Not needed yet · stock

₹55.4L

44 parts. ₹27.3L you can move now · ₹28.1L your plan uses up by 2 Mar. ₹19.4L unused for 120+ days.

Running short · parts

9 parts

Seen by SAP on 9 Oct, 4–8 working days ahead. 13 Oct: 5 still short (3 below). 2 never reached your shortage list.

Top 15 by ₹ ₹65.4L of ₹102.2L · all checked by your team · full list, with part numbers, in the Excel

#PartWhy not needed (cover)Action, by whenOwner₹LPlannerSupplier
1Long member LH V2 (finished)Not in plan; unused 168 daysSTOCKConfirm variant end, by 27 OctPlanner 1048.6Agrees
2HR coil 3.15 mm142 WDSTOCKAsk P200 to take it, by 27 OctPlanner 1016.9Agrees
3MIG wire 1.2 mm74 WD; PO 6 t due 5 NovORDERAsk to defer to 7 JanBuyer P136.3AgreesYes
4CR sheet 1.6 mm68 WD; PO 8 t due 2 NovORDERAsk to defer to 31 DecBuyer P125.8AgreesYes
5ED primer, 210 L69 WD; PO 15 drums, 3 NovORDERAsk to defer to 1 JanBuyer P134.7AgreesYes
6Cross mbr brkt LH (semi-fin.)97 WD; pressed ahead of needSTOCKUsed up by 3 FebPlanner 1034.4Agrees
7Spring hanger brkt, V2Not in plan; PO due 5 NovORDERAsk to cancel, by 21 OctBuyer P144.2AgreesYes
8Flange bolt M12×4077 WD; PO 40k pcs, 28 OctORDERAsk to defer to 11 JanBuyer P113.8AgreesYes
9Battery tray, V2 (finished)Not in plan; unused 131 daysSTOCKSell as service, by 27 OctSales (service)3.3Agrees
10Rubber bush, 40 shore96 WD; schedule release 4 NovORDERCut Nov release 11k, by 21 OctBuyer P143.1AgreesYes
11Weld nut M1088 WD; PO 1.2 lakh, 2 NovORDERAsk to defer to 23 JanBuyer P113.1AgreesYes
12Spare wheel carrier (finished)103 WDSTOCKUsed up by 1 MarPlanner 1063.0Later
13Tow hook forgingNot in plan; unused 240 daysSTOCKAsk to return, by 21 OctBuyer P142.9Agrees
14Body mount RH (semi-fin.)88 WDSTOCKUsed up by 8 FebPlanner 1032.7Later
15HR sheet 2.5 mm66 WD; PO 4 t due 27 OctORDERAsk to defer to 18 JanBuyer P122.6LaterYes

Running short what SAP showed on 9 Oct (MRP run 8 Oct), re-checked in SAP on 13 Oct · top 5 of 9 · no ₹

#PartLasts toNext receiptShort byOn your list?13 Oct checkAction, by whenOwner
1Pipe clip 25 mm15 OctPO 6,000 pcs, 21 Oct4 WDNoStill shortPhoned 13 Oct: pull in to 15 OctBuyer P11
2Arm bush16 OctSchedule release 3,000, 21 Oct3 WDYesStill shortPull in to 16 Oct (supplier must agree)Buyer P14
3Nut M819 OctNo open line—NoStill shortOrder now (4-day lead time)Buyer P11
4Gusset plate (semi-fin.)14 Oct (past)Press run 22 Oct (planner)6 WDYesFixedRun moved to 13 OctPlanner 103
5CR coil 1.2 mm19 OctPO 10 t, 23 Oct3 WDNoNot short8 t in quality inspection—

Taken out after the checks (₹24.6L): HR coil 5.0 mm ₹9.8L, mill already rolled · Cross member assy RH ₹6.6L, service order · 3 more ₹8.2L.
How to read: WD = working days. Cover = WD your stock lasts on the plan; short by = WD to the next delivery. "Later" = your planner's date. "Used up by" = stop new orders until then. Supplier = can it still change? On your list = any day 9 Oct to "lasts to". Owner = group or controller code.

What it is worth

  1. Cash: if suppliers agree, ₹46.8L due 27 Oct–5 Nov moves out (₹38.6L by about 9 weeks; ₹8.2L cancelled or cut); on 60-day terms, the payments move too.
  2. Cash you can act on now: ₹74.1L (₹46.8L of orders + ₹27.3L of stock) ₹15.5L of that stock needs a second decision (a variant write-off; plant P200 cancelling its own order). The other ₹28.1L of stock your plan uses up. This is cash freed, not savings.
  3. Doing nothing: the ₹46.8L of orders arrive and are paid on schedule, and ₹19.4L unused for 120+ days keeps ageing.

What this read could not tell you

  1. Your SAP plan vs your latest customer schedule. ₹15.3 Cr of 8-week requirement (estimate) comes from the SAP plan. Stock ₹12.0 Cr = ₹8.7 Cr needed in 8 weeks + ₹2.6 Cr needed after 8 weeks (long-lead) + ₹55.4L not needed yet + ₹0.15 Cr left out. If your next schedule is 15% lower (your planner's figure), stock not needed rises about ₹1.3 Cr (estimate).
  2. Real supplier lead times. The order list uses lead times as ordered.
  3. MRP controllers 107–109 (outside your planner's access): ₹2.6 Cr (18%) of stock not read; other plants not read.

How we checked the numbers

Next: Supply-Base Diagnostic · 4 weeks · this plant · fixed price

Now: act on the 3 parts still short, the 28 order lines and the ₹27.3L of stock you can move. The Diagnostic adds a daily short list, the ₹1.3 Cr at risk if schedules drop 15%, the ₹2.6 Cr of stock not read, lines 16+ (₹36.8L) on your new schedule and real lead times. It ends with a list of cash to release, signed off by your planning head and finance.

Next step Owner By